A groundbreaking for the
Linear Accelerator was held with the neighboring communities on a snowy
December 1, 1968. The Booster Ring and the four-mile Main Ring were
constructed between 1969 - 1971. Once the final magnet was installed
in the Main Ring on April 16, 1971, the fine-tuning of this unprecedented
scientific tool began. After a stressful commissioning period the design
energy was finally reached in March 1972. The task had been completed
faster and for less money than anyone had dreamed possible. The entire
staff celebrated
this momentous milestone in the basement of the new Central Laboratory,
then only a few stories high. |